REGULATION (EC) No. 714/2009

OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL ON CONDITIONS FOR ACCESS TO THE NETWORK FOR CROSS-BORDER  EXCHANGES IN ELECTRICITY AND REPEALING REGULATION (EC) No 1228/2003

 

(Brussels, 13.VII.2009)

(Text with EEA relevance)

(Amended by Regulation (EU) No 347/2013 of the European Parliament and of the Council of 17 April 2013, Commission Regulation (EU) No 543/2013 of 14 June 2013)

 

The European Parliament and the Council of the European Union,

Having regard to the Treaty establishing the European Community, and in particular Article 95 thereof,

Having regard to the proposal from the Commission,

Having regard to the opinion of the European Economic and Social Committee <*>,

———————————

<*> OJ C 211, 19.8.2008, p. 23.

 

Having regard to the opinion of the Committee of the Regions <*>,

———————————

<*> OJ C 172, 5.7.2008, p. 55.

 

Acting in accordance with the procedure laid down in Article 251 of the Treaty <*>,

———————————

<*> Opinion of the European Parliament of 18 June 2008 (not yet published in the Official Journal), Council Common Position of 9 January 2009 (OJ C 75 E, 31.3.2009, p. 16) and Position of the European Parliament of 22 April 2009 (not yet published in the Official Journal). Council Decision of 25 June 2009.

 

Whereas:

(1) The internal market in electricity, which has been progressively implemented since 1999, aims to deliver real choice for all consumers in the Community, be they citizens or businesses, new business opportunities and more cross-border trade, so as to achieve efficiency gains, competitive prices and higher standards of service, and to contribute to security of supply and sustainability.

(2) Directive 2003/54/EC of the European Parliament and of the Council of 26 June 2003 concerning common rules for the internal market in electricity <*> and Regulation (EC) No 1228/2003 of the European Parliament and of the Council of 26 June 2003 on conditions for access to the network for cross-border exchanges in electricity <**> have made significant contributions towards the creation of such an internal market in electricity.

———————————

<*> OJ L 176, 15.7.2003, p. 37.

<**> OJ L 176, 15.7.2003, p. 1.

 

(3) However, at present, there are obstacles to the sale of electricity on equal terms, without discrimination or disadvantage in the Community. In particular, non-discriminatory network access and an equally effective level of regulatory supervision do not yet exist in each Member State, and isolated markets persist.

(4) The Communication of the Commission of 10 January 2007 entitled «An Energy Policy for Europe» highlighted the importance of completing the internal market in electricity and creating a level playing field for all electricity undertakings in the Community. The Communications of the Commission of 10 January 2007 entitled «Prospects for the internal gas and electricity market» and «Inquiry pursuant to Article 17 of Regulation (EC) No 1/2003 into the European gas and electricity sectors (Final Report)» demonstrated that the present rules and measures neither provide the necessary framework nor provide for the creation of interconnection capacities to achieve the objective of a well-functioning, efficient and open internal market.

(5) In addition to thoroughly implementing the existing regulatory framework, the regulatory framework for the internal market in electricity set out in Regulation (EC) No 1228/2003 should be adapted in line with those communications.

(6) In particular, increased cooperation and coordination among transmission system operators is required to create network codes for providing and managing effective and transparent access to the transmission networks across borders, and to ensure coordinated and sufficiently forward-looking planning and sound technical evolution of the transmission system in the Community, including the creation of interconnection capacities, with due regard to the environment. Those network codes should be in line with framework guidelines, which are non-binding in nature (framework guidelines) and which are developed by the Agency for the Cooperation of Energy Regulators established by Regulation (EC) No 713/2009 of the European Parliament and of the Council of 13 July 2009 establishing an Agency for the Cooperation of Energy Regulators <*> (the Agency). The Agency should have a role in reviewing, based on matters of fact, draft network codes, including their compliance with the framework guidelines, and it should be enabled to recommend them for adoption by the Commission. The Agency should assess proposed amendments to the network codes and it should be enabled to recommend them for adoption by the Commission. Transmission system operators should operate their networks in accordance with those network codes.

———————————

<*> See page 1 of this Official Journal.

 

(7) In order to ensure optimal management of the electricity transmission network and to allow trading and supplying electricity across borders in the Community, a European Network of Transmission System Operators for Electricity (the ENTSO for Electricity), should be established. The tasks of the ENTSO for Electricity should be carried out in compliance with Community competition rules which remain applicable to the decisions of the ENTSO for Electricity. The tasks of the ENTSO for Electricity should be well-defined and its working method should ensure efficiency, transparency and the representative nature of the ENTSO for Electricity. The network codes prepared by the ENTSO for Electricity are not intended to replace the necessary national network codes for non-cross-border issues. Given that more effective progress may be achieved through an approach at regional level, transmission system operators should set up regional structures within the overall cooperation structure, whilst ensuring that results at regional level are compatible with network codes and non-binding ten-year network development plans at Community level. Member States should promote cooperation and monitor the effectiveness of the network at regional level. Cooperation at regional level should be compatible with progress towards a competitive and efficient internal market in electricity.

(8) All market participants have an interest in the work expected of the ENTSO for Electricity. An effective consultation process is therefore essential and existing structures that are set up to facilitate and streamline the consultation process, such as the Union for the Coordination of Transmission of Electricity, national regulators or the Agency, should play an important role.

(9) In order to ensure greater transparency regarding the entire electricity transmission network in the Community, the ENTSO for Electricity should draw up, publish and regularly update a non-binding Community-wide ten-year network development plan (Community-wide network development plan). Viable electricity transmission networks and necessary regional interconnections, relevant from a commercial or security of supply point of view, should be included in that network development plan.

(10) This Regulation should lay down basic principles with regard to tarification and capacity allocation, whilst providing for the adoption of Guidelines detailing further relevant principles and methodologies, in order to allow rapid adaptation to changed circumstances.

(11) In an open, competitive market, transmission system operators should be compensated for costs incurred as a result of hosting cross-border flows of electricity on their networks by the operators of the transmission systems from which cross-border flows originate and the systems where those flows end.

(12) Payments and receipts resulting from compensation between transmission system operators should be taken into account when setting national network tariffs.

(13) The actual amount payable for cross-border access to the system can vary considerably, depending on the transmission system operator involved and as a result of differences in the structure of the tarification systems applied in Member States. A certain degree of harmonisation is therefore necessary in order to avoid distortions of trade.

(14) A proper system of long-term locational signals is necessary, based on the principle that the level of the network access charges should reflect the balance between generation and consumption of the region concerned, on the basis of a differentiation of the network access charges on producers and/or consumers.

(15) It would not be appropriate to apply distance-related tariffs or, provided appropriate locational signals are in place, a specific tariff to be paid only by exporters or importers in addition to the general charge for access to the national network.

(16) The precondition for effective competition in the internal market in electricity is non-discriminatory and transparent charges for network use including interconnecting lines in the transmission system. The available capacity of those lines should be set at the maximum levels consistent with the safety standards of secure network operation.

(17) It is important to avoid distortion of competition resulting from the differing safety, operational and planning standards used by transmission system operators in Member States. Moreover, there should be transparency for market participants concerning available transfer capacities and the security, planning and operational standards that affect the available transfer capacities.

(18) Market monitoring undertaken over recent years by the national regulatory authorities and by the Commission has shown that current transparency requirements and rules on access to infrastructure are not sufficient to secure a genuine, well-functioning, open and efficient internal market in electricity.

(19) Equal access to information on the physical status and efficiency of the system is necessary to enable all market participants to assess the overall demand and supply situation and identify the reasons for movements in the wholesale price. This includes more precise information on electricity generation, supply and demand including forecasts, network and interconnection capacity, flows and maintenance, balancing and reserve capacity.

(20) To enhance trust in the market, its participants need to be sure that those engaging in abusive behaviour can be subject to effective, proportionate and dissuasive penalties. The competent authorities should be given the competence to investigate effectively allegations of market abuse. To that end, it is necessary that competent authorities have access to data that provides information on operational decisions made by supply undertakings. In the electricity market, many relevant decisions are made by the generators, which should keep information in relation thereto available to and easily accessible by the competent authorities for a fixed period of time. The competent authorities should, furthermore, regularly monitor the compliance of the transmission system operators with the rules. Small generators with no real ability to distort the market should be exempt from that obligation.

(21) There should be rules on the use of revenues flowing from congestion-management procedures, unless the specific nature of the interconnector concerned justifies an exemption from those rules.

(22) The management of congestion problems should provide correct economic signals to transmission system operators and market participants and should be based on market mechanisms.

(23) Investments in major new infrastructure should be promoted strongly while ensuring the proper functioning of the internal market in electricity. In order to enhance the positive effect of exempted direct current interconnectors on competition and security of supply, market interest during the project-planning phase should be tested and congestion-management rules should be adopted. Where direct current interconnectors are located in the territory of more than one Member State, the Agency should handle as a last resort the exemption request in order to take better account of its cross-border implications and to facilitate its administrative handling. Moreover, given the exceptional risk profile of constructing those exempt major infrastructure projects, undertakings with supply and production interests should be able to benefit from a temporary derogation from the full unbundling rules for the projects concerned. Exemptions granted under Regulation (EC) No 1228/2003 continue to apply until the scheduled expiry date as decided in the granted exemption decision.

(24) To ensure the smooth functioning of the internal market in electricity, provision should be made for procedures which allow the adoption of decisions and Guidelines with regard, inter alia, to tarification and capacity allocation by the Commission whilst ensuring the involvement of Member States’ regulatory authorities in that process, where appropriate through their European association. Regulatory authorities, together with other relevant authorities in the Member States, have an important role to play in contributing to the proper functioning of the internal market in electricity.

(25) National regulatory authorities should ensure compliance with the rules contained in this Regulation and the Guidelines adopted pursuant thereto.

(26) The Member States and the competent national authorities should be required to provide relevant information to the Commission. Such information should be treated confidentially by the Commission. Where necessary, the Commission should have an opportunity to request relevant information directly from undertakings concerned, provided that the competent national authorities are informed.

(27) Member States should lay down rules on penalties applicable to infringements of the provisions of this Regulation and ensure that they are implemented. Those penalties must be effective, proportionate and dissuasive.

(28) The measures necessary for the implementation of this Regulation should be adopted in accordance with Council Decision 1999/468/EC of 28 June 1999 laying down the procedures for the exercise of implementing powers conferred on the Commission <*>.

———————————

<*> OJ L 184, 17.7.1999, p. 23.

 

(29) In particular, the Commission should be empowered to establish or adopt the Guidelines necessary for providing the minimum degree of harmonisation required to achieve the aims of this Regulation. Since those measures are of general scope and are designed to amend non-essential elements of this Regulation, by supplementing it with new non-essential elements, they must be adopted in accordance with the regulatory procedure with scrutiny provided for in Article 5a of Decision 1999/468/EC.

(30) Since the objective of this Regulation, namely the provision of a harmonised framework for cross-border exchanges of electricity, cannot be sufficiently achieved by the Member States and can therefore be better achieved at Community level, the Community may adopt measures, in accordance with the principle of subsidiarity, as set out in Article 5 of the Treaty. In accordance with the principle of proportionality, as set out in that Article, this Regulation does not go beyond what is necessary in order to achieve that objective.

(31) Given the scope of the amendments that are being made herein to Regulation (EC) No 1228/2003, it is desirable, for reasons of clarity and rationalisation, that the provisions in question should be recast by bringing them all together in a single text in a new Regulation,

Have adopted this Regulation:

 

Article 1

Subject-matter and scope

 

This Regulation aims at:

(a) setting fair rules for cross-border exchanges in electricity, thus enhancing competition within the internal market in electricity, taking into account the particular characteristics of national and regional markets. This will involve the establishment of a compensation mechanism for cross-border flows of electricity and the setting of harmonised principles on cross-border transmission charges and the allocation of available capacities of interconnections between national transmission systems;

(b) facilitating the emergence of a well-functioning and transparent wholesale market with a high level of security of supply in electricity. It provides for mechanisms to harmonise the rules for cross-border exchanges in electricity.

 

Article 2

Definitions

 

  1. For the purpose of this Regulation, the definitions contained in Article 2 of Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in electricity <*> apply, with the exception of the definition of «interconnector» which shall be replaced by the following:

———————————

<*> See page 55 of this Official Journal.

 

— «interconnector» means a transmission line which crosses or spans a border between Member States and which connects the national transmission systems of the Member States.

  1. The following definitions shall apply:

(a) «regulatory authorities» means the regulatory authorities referred to in Article 35(1) of Directive 2009/72/EC;

(b) «cross-border flow» means a physical flow of electricity on a transmission network of a Member State that results from the impact of the activity of producers and/or consumers outside that Member State on its transmission network;

(c) «congestion» means a situation in which an interconnection linking national transmission networks cannot accommodate all physical flows resulting from international trade requested by market participants, because of a lack of capacity of the interconnectors and/or the national transmission systems concerned;

(d) «declared export» means the dispatch of electricity in one Member State on the basis of an underlying contractual arrangement to the effect that the simultaneous corresponding take-up (declared import) of electricity will take place in another Member State or a third country;

(e) «declared transit» means a circumstance where a declared export of electricity occurs and where the nominated path for the transaction involves a country in which neither the dispatch nor the simultaneous corresponding take-up of the electricity will take place;

(f) «declared import» means the take-up of electricity in a Member State or a third country simultaneously with the dispatch of electricity (declared export) in another Member State;

(g) «new interconnector» means an interconnector not completed by 4 August 2003.

For the purpose of the inter-transmission system operator compensation mechanism referred to in Article 13 only, where transmission networks of two or more Member States form part, in whole or in part, of a single control block, the control block as a whole shall be considered as forming part of the transmission network of one of the Member States concerned, in order to avoid flows within control blocks being considered as cross-border flows under point (b) of the first subparagraph of this paragraph and giving rise to compensation payments under Article 13. The regulatory authorities of the Member States concerned may decide which of the Member States concerned shall be that of which the control block as a whole is to be considered to form part.

 

Article 3

Certification of transmission system operators

 

  1. The Commission shall examine any notification of a decision on the certification of a transmission system operator as laid down in Article 10(6) of Directive 2009/72/EC as soon as it is received. Within two months of the day of receipt of such notification, the Commission shall deliver its opinion to the relevant national regulatory authority as to its compatibility with Article 10(2) or Article 11, and Article 9 of Directive 2009/72/EC.

When preparing the opinion referred to in the first subparagraph, the Commission may request the Agency to provide its opinion on the national regulatory authority’s decision. In such a case, the two-month period referred to in the first subparagraph shall be extended by two further months.

In the absence of an opinion by the Commission within the periods referred to in the first and second subparagraphs, the Commission shall be deemed not to raise objections to the regulatory authority’s decision.

  1. Within two months of receiving an opinion of the Commission, the national regulatory authority shall adopt its final decision regarding the certification of the transmission system operator, taking the utmost account of that opinion. The regulatory authority’s decision and the Commission’s opinion shall be published together.
  2. At any time during the procedure, regulatory authorities and/or the Commission may request from a transmission system operator and/or an undertaking performing any of the functions of generation or supply any information relevant to the fulfilment of their tasks under this Article.
  3. Regulatory authorities and the Commission shall preserve the confidentiality of commercially sensitive information.
  4. The Commission may adopt Guidelines setting out the details of the procedure to be followed for the application of paragraphs 1 and 2 of this Article. Those measures, designed to amend non-essential elements of this Regulation by supplementing it, shall be adopted in accordance with the regulatory procedure with scrutiny referred to in Article 23(2).
  5. Where the Commission has received notification of the certification of a transmission system operator under Article 9(10) of Directive 2009/72/EC, the Commission shall take a decision relating to certification. The regulatory authority shall comply with the Commission decision.

 

Article 4

European network of transmission system operators for electricity

 

All transmission system operators shall cooperate at Community level through the ENTSO for Electricity, in order to promote the completion and functioning of the internal market in electricity and cross-border trade and to ensure the optimal management, coordinated operation and sound technical evolution of the European electricity transmission network.

 

Article 5

Establishment of the ENTSO for Electricity

 

  1. By 3 March 2011, the transmission system operators for electricity shall submit to the Commission and to the Agency the draft statutes, a list of members and draft rules of procedure, including the rules of procedures on the consultation of other stakeholders, of the ENTSO for Electricity to be established.
  2. Within two months of the day of the receipt, the Agency, after formally consulting the organisations representing all stakeholders, in particular the system users, including customers, shall provide an opinion to the Commission on the draft statutes, list of members and draft rules of procedure.
  3. The Commission shall deliver an opinion on the draft statutes, list of members and draft rules of procedures taking into account the opinion of the Agency provided for in paragraph 2 and within three months of the day of the receipt of the opinion of the Agency.
  4. Within three months of the day of receipt of the Commission’s opinion, the transmission system operators shall establish the ENTSO for Electricity and adopt and publish its statutes and rules of procedure.

 

Article 6

Establishment of network codes

 

  1. The Commission shall, after consulting the Agency, the ENTSO for Electricity and the other relevant stakeholders, establish an annual priority list identifying the areas set out in Article 8(6) to be included in the development of network codes.
  2. The Commission shall request the Agency to submit to it within a reasonable period of time not exceeding six months a non-binding framework guideline (framework guideline) setting out clear and objective principles, in accordance with Article 8(7), for the development of network codes relating to the areas identified in the priority list. Each framework guideline shall contribute to non-discrimination, effective competition and the efficient functioning of the market. Upon a reasoned request from the Agency, the Commission may extend that period.
  3. The Agency shall formally consult the ENTSO for Electricity and the other relevant stakeholders in regard to the framework guideline, during a period of no less than two months, in an open and transparent manner.
  4. If the Commission considers that the framework guideline does not contribute to non-discrimination, effective competition and the efficient functioning of the market, it may request the Agency to review the framework guideline within a reasonable period of time and re-submit it to the Commission.
  5. If the Agency fails to submit or re-submit a framework guideline within the period set by the Commission under paragraphs 2 or 4, the Commission shall elaborate the framework guideline in question.
  6. The Commission shall request the ENTSO for Electricity to submit a network code which is in line with the relevant framework guideline, to the Agency within a reasonable period of time not exceeding 12 months.
  7. Within a period of three months of the day of the receipt of a network code, during which the Agency may formally consult the relevant stakeholders, the Agency shall provide a reasoned opinion to the ENTSO for Electricity on the network code.
  8. The ENTSO for Electricity may amend the network code in the light of the opinion of the Agency and re-submit it to the Agency.
  9. When the Agency is satisfied that the network code is in line with the relevant framework guideline, the Agency shall submit the network code to the Commission and may recommend that it be adopted within a reasonable time period. The Commission shall provide reasons in the event that it does not adopt that network code.
  10. Where the ENTSO for Electricity has failed to develop a network code within the period of time set by the Commission under paragraph 6, the Commission may request the Agency to prepare a draft network code on the basis of the relevant framework guideline. The Agency may launch a further consultation in the course of preparing a draft network code under this paragraph. The Agency shall submit a draft network code prepared under this paragraph to the Commission and may recommend that it be adopted.
  11. The Commission may adopt, on its own initiative, where the ENTSO for Electricity has failed to develop a network code, or the Agency has failed to develop a draft network code as referred to in paragraph 10 of this Article, or upon recommendation of the Agency under paragraph 9 of this Article, one or more network codes in the areas listed in Article 8(6).

Where the Commission proposes to adopt a network code on its own initiative, the Commission shall consult the Agency, the ENTSO for Electricity and all relevant stakeholders in regard to the draft network code during a period of no less than two months. Those measures, designed to amend non-essential elements of this Regulation by supplementing it, shall be adopted in accordance with the regulatory procedure with scrutiny referred to in Article 23(2).

  1. This Article shall be without prejudice to the Commission’s right to adopt and amend the Guidelines as laid down in Article 18.

 

Article 7

Amendments of network codes

 

  1. Draft amendments to any network code adopted under Article 6 may be proposed to the Agency by persons who are likely to have an interest in that network code, including the ENTSO for Electricity, transmission system operators, system users and consumers. The Agency may also propose amendments on its own initiative.
  2. The Agency shall consult all stakeholders in accordance with Article 10 of Regulation (EC) No 713/2009. Following that process, the Agency may make reasoned proposals for amendments to the Commission, explaining how such proposals are consistent with the objectives of the network codes set out in Article 6(2).
  3. The Commission may adopt, taking account of the Agency’s proposals, amendments to any network code adopted under Article 6. Those measures, designed to amend non-essential elements of this Regulation by supplementing it, shall be adopted in accordance with the regulatory procedure with scrutiny referred to in Article 23(2).
  4. Consideration of proposed amendments under the procedure set out in Article 23(2) shall be limited to consideration of the aspects related to the proposed amendment. Those proposed amendments are without prejudice to other amendments which the Commission may propose.

 

Article 8

Tasks of the ENTSO for Electricity

 

  1. The ENTSO for Electricity shall elaborate network codes in the areas referred to in paragraph 6 of this Article upon a request addressed to it by the Commission in accordance with Article 6(6).
  2. The ENTSO for Electricity may elaborate network codes in the areas set out in paragraph 6 with a view to achieving the objectives set out in Article 4 where those network codes do not relate to areas covered by a request addressed to it by the Commission. Those network codes shall be submitted to the Agency for an opinion. That opinion shall be duly taken into account by the ENTSO for Electricity.
  3. The ENTSO for Electricity shall adopt:

(a) common network operation tools to ensure coordination of network operation in normal and emergency conditions, including a common incident classification scale, and research plans. These tools shall specify inter alia:

(i) the information, including appropriate day ahead, intra-day and real-time information, useful for improving operational coordination, as well as the optimal frequency for the collection and sharing of such information;

(ii) the technological platform for the exchange of information in real time and where appropriate, the technological platforms for the collection, processing and transmission of the other information referred to in point (i), as well as for the implementation of the procedures capable of increasing operational coordination between transmission system operators with a view to such coordination becoming Union-wide;

(iii) how transmission system operators make available the operational information to other transmission system operators or any entity duly mandated to support them to achieve operational coordination, and to the Agency; and

(iv) that transmission system operators designate a contact point in charge of answering inquiries from other transmission system operators or from any entity duly mandated as referred to in point (iii), or from the Agency concerning such information.

The ENTSO for Electricity shall submit the adopted specifications on points (i) to (iv) above to the Agency and to the Commission by 16 May 2015.

Within 12 months of the adoption of the specifications, the Agency shall issue an opinion in which it considers whether they sufficiently contribute to the promotion of cross-border trade and to ensuring the optimal management, coordinated operation, efficient use and sound technical evolution of the European electricity transmission network;

(b) a non-binding Community-wide ten-year network development plan, (Community-wide network development plan), including a European generation adequacy outlook, every two years;

(c) recommendations relating to the coordination of technical cooperation between Community and third-country transmission system operators;

(d) an annual work programme;

(e) an annual report;

(f) annual summer and winter generation adequacy outlooks.

  1. The European generation adequacy outlook referred to in point (b) of paragraph 3 shall cover the overall adequacy of the electricity system to supply current and projected demands for electricity for the next five-year period as well as for the period between five and 15 years from the date of that outlook. The European generation adequacy outlook shall build on national generation adequacy outlooks prepared by each individual transmission system operator.
  2. The annual work programme referred to in point (d) of paragraph 3 shall contain a list and description of the network codes to be prepared, a plan on coordination of operation of the network, and research and development activities, to be realised in that year, and an indicative calendar.
  3. The network codes referred to in paragraphs 1 and 2 shall cover the following areas, taking into account, if appropriate, regional specificities:

(a) network security and reliability rules including rules for technical transmission reserve capacity for operational network security;

(b) network connection rules;

(c) third-party access rules;

(d) data exchange and settlement rules;

(e) interoperability rules;

(f) operational procedures in an emergency;

(g) capacity-allocation and congestion-management rules;

(h) rules for trading related to technical and operational provision of network access services and system balancing;

(i) transparency rules;

(j) balancing rules including network-related reserve power rules;

(k) rules regarding harmonised transmission tariff structures including locational signals and inter-transmission system operator compensation rules; and

(l) energy efficiency regarding electricity networks.

  1. The network codes shall be developed for cross-border network issues and market integration issues and shall be without prejudice to the Member States’ right to establish national network codes which do not affect cross-border trade.
  2. The ENTSO for Electricity shall monitor and analyse the implementation of the network codes and the Guidelines adopted by the Commission in accordance with Article 6(11), and their effect on the harmonisation of applicable rules aimed at facilitating market integration. The ENTSO for Electricity shall report its findings to the Agency and shall include the results of the analysis in the annual report referred to in point (e) of paragraph 3 of this Article.
  3. The ENTSO for Electricity shall make available all information required by the Agency to fulfil its tasks under Article 9(1).
  4. The ENTSO for Electricity shall adopt and publish a Community-wide network development plan every two years. The Community-wide network development plan shall include the modelling of the integrated network, scenario development, a European generation adequacy outlook and an assessment of the resilience of the system.

The Community-wide network development plan shall, in particular:

(a) build on national investment plans, taking into account regional investment plans as referred to in Article 12(1), and, if appropriate, Union aspects of network planning as set out in Regulation (EU) No 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure <*>; it shall be subject to a cost-benefit analysis using the methodology established as set out in Article 11 of that Regulation;

———————————

<*> OJ L 262, 22.9.2006, p. 1.

 

(b) regarding cross-border interconnections, also build on the reasonable needs of different system users and integrate long-term commitments from investors referred to in Article 8 and Articles 13 and 22 of Directive 2009/72/EC; and

(c) identify investment gaps, notably with respect to cross-border capacities.

In regard to point (c) of the second subparagraph, a review of barriers to the increase of cross-border capacity of the network arising from different approval procedures or practices may be annexed to the Community-wide network development plan.

  1. The Agency shall provide an opinion on the national ten-year network development plans to assess their consistency with the Community-wide network development plan. If the Agency identifies inconsistencies between a national ten-year network development plan and the Community-wide network development plan, it shall recommend amending the national ten-year network development plan or the Community-wide network development plan as appropriate. If such national ten-year network development plan is elaborated in accordance with Article 22 of Directive 2009/72/EC, the Agency shall recommend that the competent national regulatory authority amend the national ten-year network development plan in accordance with Article 22(7) of that Directive and inform the Commission thereof.

12. Upon request of the Commission, the ENTSO for Electricity shall give its views to the Commission on the adoption of the Guidelines as laid down in Article 18.